Expansion works of Komárom municipal wastewater treatment plan took place between December 2019 an June 2021, during which Inwatech Kft. was contracted to perfom the following tasks:

As a result of the investment, the hydraulic capacity increased from 4,500m3/day to 8,000 m3/day and the biological capacity to 57,067 PE. During the trial period, the quality of the treated wastewater was shown to meet the requirements for all limit values.

Wastewater treatment technology at Komárom WWTP consists of: